External works
- Window replacements are progressing well on Levels 2 and 3.
- Concrete panels and glazing to the front elevation have been removed and will be replaced with curtain wall glazing.
- Bath Stone cladding is progressing to the new lift shaft on the South elevation and is due to be completed this week.
- The front courtyard waterproofing and tanking works are progressing.
- Roofing works are complete and the new air handling unit will be lifting onto the roof with a mobile crane.
Access routes across the site are maintained for the University staff working on Level 4. The access routes will be amended as the works progress.
Internal works
Level 1
- Internal tanking and waterproofing works are complete.
- Mechanical, Electrical and Carpentry works are progressing well.
- Plasterboarding is ongoing and plastering will follow.
Level 2
- Mechanical, Electrical and Carpentry works are progressing well.
- Decorations and finishes works have commenced.
Level 3
- The toilet refurbishments are complete and handed over for use by occupants.
- The staff have now been relocated from the South end of Level 4 onto Level 3 in preparation for the lift shaft breakthroughs.
All works on Level 3 will be completed by the end of November.